Case Study:
Year: |
1997 |
Client: |
Alstom |
Location: |
USA |
Subject: |
3D measurements
on steam turbines in nuclear plant |
Volume of environment
or object (meters):
|
8x6 |
Number of
points: |
700,000 |
Duration: |
6 Hours |
Overall accuracy
required: |
2 cm |
Overall accuracy
achieved |
5 mm |
Supplying clouds
of points to CATIA
Objective/Project
Requirements:
Retrofit of competitor's
steam turbines during outages and without
any drawings.
Client requires accurate measurements on rotor, inner casings,
exhaust hoods and blades.